问题

The()defines the phases that connect


The()defines the phases that connect the beginning of a project to its end.

  • Aschedule
  • Bproject life cycle
  • Ctemporary
  • Dmilestone
参考答案
参考解析:

该题的关键词为"phases",其语句结构为"______(主语)defines(谓语)the phases",含义为"什么定义了项目的多个阶段",通过筛选首先排除A和C,选项D也容易排除,因为Milestone(里程碑)只是关键点上发生的活动,不具备阶段的持续性特点,因而只能选择选项B。

分类:专业英语题库,高级信息系统项目管理师题库
相关推荐

1、In the operate phase

In the operate phase, providing and maintaining reliable, current information about the WLA...

2、In the plan phase,&#

In the plan phase, network readiness assessment addresses which customer need? Select exact...

3、In the Cisco IOS, what is the definiti

In the Cisco IOS, what is the definition of a global command?()A A command that can be entered in any configuration mode.B A command that ...

4、The company which is defined in the IS

The company which is defined in the ISM Code means()Athe owner of the shipBthe manager who assumes the responsibility for operation of the shipCthe bareboat chartererDAll of the above

5、As defined in the Rules,the term vesse

As defined in the Rules,the term vessel includes().AseaplanesBnon-displacement craftCbargesDAll of the above

6、In the operate phase

In the operate phase, providing and maintaining reliable, current information about the wla...