问题

()is a type of bar chart that illustra


()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.

  • AA、gantt chart
  • BB、project histogram
  • CC、milestone chart
  • DD、project flowchart
参考答案
参考解析:

分类:信息系统项目管理师综合练习题库,高级信息系统项目管理师题库
相关推荐

1、It is a type of desert bush that can()

It is a type of desert bush that can()extremes of temperature.AadaptBwithdrawCwithstandDshade

2、A(n) () is a special type of valve whi

A(n) () is a special type of valve which prevents the passage of steam but allows condensate to pass.Acheck valveBnon-return valveCsteam trapDquick closing tra

3、()is not a type of IALA maritime buoya

()is not a type of IALA maritime buoyage system.Aspecial marksBisolated danger marksCcardinal marksDfore and aft mark

4、Which type of precipitation is a produ

Which type of precipitation is a product of the violent convection found in thunderstorms().ASnowBFreezing RainCHailDSleet

5、The revision date of a chart is printe

The revision date of a chart is printed on which area of the chart? ()ATop centerBLower-left cornerCPart of the chart titleDAny clear area around the neat line

6、The marine diesel engine is a type of

The marine diesel engine is a type of diesel engine used on ships The () of its operation is not very difficult to understand.AprincipleBprincipalCcauseDcase