The project()is a key input to qualit


The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

  • Awork performance information
  • Bscope statement
  • Cchangerequests
  • Dprocess analysis
参考答案
参考解析:

该题的关键词为"major project deliverables、the project objectives",其语句结构为"The project (主语)is(谓语)akey input to quality planning(表语)since it documentsmaj or proj ect deliverables,the project objectives(原因状语从句)",含义为"项目的什么是质量计划的一个关键输入,因为它记录了主要的项目交付物和项目目标",容易判断出应该为项目范围说明书的作用,应该选择选项B。

分类:专业英语题库,高级信息系统项目管理师题库
相关推荐

1、The project(73)is a key input to quali

The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define imp...

2、●In the following, the input device is

●In the following, the input device is _(72) .(72)A keyboardB monitorC printerD plotter

3、The way to reduce () is to build up a

The way to reduce () is to build up a film of lubricant between any two surfaces that rub against each other.AfrictionBcollisionCinertiaDresistance

4、The projection on a shaft designed to

The projection on a shaft designed to change circular motion into up and down or back and fore motion is called ().AwheelBcrankshaftCrunning gearDcam

5、● The project schedule is more than a

● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is...

6、A charterer is unable to complete the

A charterer is unable to complete the loading of a vessel during the lay days specified in the charter party. Under these circumstances,the(...