You create two resou


You create two resource plans, one for data warehouse loading jobs at night and the other for application jobs at day time. You want the resource plans to activate automatically so that the resource allocation is optimum as desired by the activity.How would you achieve this? ()

  • AImplement job classes 
  • BImplement Scheduler windows
  • CImplement the mapping rule for the consumer groups 
  • DSet the SWITCH_TIME resource plan directive for both the resource pla
参考答案
参考解析: