In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication. According to Metcalfe’s Law, a project with 10 stakeholders has () potential communication channels.
- AA、10
- BB、45
- CC、50
- DD、100