可学答题网 > 问答 > 专业英语题库,高级信息系统项目管理师题库
目录: 标题| 题干| 答案| 搜索| 相关
问题

Estimating schedule activity costs in


Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.空白(1)处填()

  • AA.accuracy
  • Bapproximation
  • Cspecification
  • Dsummary
参考答案
参考解析:

阅读试题可知,整段文章讨论的内容集中于"Costestimating",分析问题(1)的语句结构为"estimatingscheduleactivitycosts(主语)involves(谓语)developingan (1) ofthecostoftheresources"。接下来使用排除法,如果对于"estimatingscheduleactivitycosts"的特定内容不了解,似乎哪个选项也可以,注意"thelresourcesneededtocompleteeachscheduleactivity",既然每项活动所需的资源都需考虑,那就只能选择答案summary,summary在此处解释为"汇总"。分析问题(2)对应的语句,"costestimates(主语)aregenerallyexpressed(谓语)inunitsof (2) tofacilitatecomparisonsbothwithinandacrossprojects",结合选项,此句的含义为"成本估算(结果)通常以作为单位",故而只能选择C,Currency的含义为"货币"、"通货",考生即使不熟悉这个单词,也能轻易排除其他三个选项。问题(3)对应的语句,"the (3)(主语)describes(谓语)importantinformationaboutprojectrequirementthatisconsideredduringcostestimating",所以该句的含义即"描述了成本估算时应考虑的项目需求"。显而易见,选项C和D容易排除,但选择"Projectscopestatement"还是"Scopeofwork"?Scopeofwork(工作说明书)是合同中的附件,用于说明合同的工作范围(此时项目尚未建立),因而选择选项A。

分类:专业英语题库,高级信息系统项目管理师题库
相关推荐

1、Activity Based Costing (ABC) is an(36)

Activity Based Costing (ABC) is an(36)technique that allows an organization to determine the actual(37)associated with each product and service pr...

2、In America,where labor(劳工) costs are s

In America,where labor(劳工) costs are so high,"do-it-yourself" is a way of life.Many people (1) their own cars,build their own garages,and ...

3、In approximating costs, the estimator

In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .AbudgetBplanCriskDcontract

4、Estimating activity durations uses inf

Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.AmilestoneBbaselineCqualityDwork

5、Estimating activity durations uses in

Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.AmilestoneBbaselineCqualityDwork

6、The process of(72)schedule activity du

The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.AestimatingBdefiningCplanningDsequencing