Developing the project schedule is of


Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.

  • Aanalyze
  • Btrack
  • Clevel
  • Dextend
参考答案
参考解析:

该题的关键词为"project schedule、 baseline",其主要的语句结构为一个定语从句结构"project schedule that (主语)can serve as (谓语)a baseline to_progress",含义为"项目进度可以作为怎么样项目进展的基线",根据题意,容易判断对项目进度进行跟踪,所以选择选项B。

分类:专业英语题库,高级信息系统项目管理师题库
相关推荐

1、One of the scheduler

One of the schedulers has submitted an ad hoc job to list a particular directory....

2、The projecting lugs of the rudderpost

The projecting lugs of the rudderpost which furnish support to the rudder are called().AbasesBgudgeonsCpintlesDrudder lug

3、● The project schedule is more than a

● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is...

4、The inputs of developing project mana

The inputs of developing project management plan do not include()Aproject charterBstakeholder management strategyCproject scope statementDoutputs from planning processes

5、● The inputs of developing project man

● The inputs of developing project management plan do not include (72).(72)A project charterB stakeholder management strategyC project scope statementD outputs from planning processes

6、The process of(72)schedule activity du

The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.AestimatingBdefiningCplanningDsequencing