Estimating activity durations uses in


Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.

  • Amilestone
  • Bbaseline
  • Cquality
  • Dwork
参考答案
参考解析:

该题的关键词为"required resource types、estimated resource quantities、 resource calendars",其语句结构为"Estimating activity durations(主语)uses(谓语)information on activity scope of_____(宾语)",含义为"估算活动工期应用什么活动范围的信息",结合前面的关键词,此处应该识别出估算活动工期对应的输入项,因而选择工作范围,选择选项D。

分类:专业英语题库,高级信息系统项目管理师题库
相关推荐

1、All the activities are in the afternoo

All the activities are in the afternoon except ____ .A Exercises ClassB Travel LectureC Sewing ClassD Painting

2、Estimating schedule activity costs in

Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimat...

3、Your company uses Active Directory-int

Your company uses Active Directory-integrated DNS. Users require access to the Internet.You run a network capture.You notice the DNS server is s...

4、The unit of duration of a dash in Mors

The unit of duration of a dash in Morse Code is().Aone and one-half times the length of a dotBtwice the length of a dotCthree times the length of a dotDfour times the length of a dot

5、He took()part in the activity.

He took()part in the activity.Aan activeBa dynamicCa positiveDenergetic

6、Radio beacon can be activated()in case

Radio beacon can be activated()in case of distress.Aonly automaticallyBonly manuallyCboth automatically and manuallyDonly by remote control